OHIO TURNPIKE COMMISSION
Resolution Awarding a Contract to Perform Construction
for the Noise Mitigation Pilot Project
WHEREAS, the Commission duly advertised according to law for bids under Contract
No. 62-09-01 / 62-09-02 for the construction required to perform a Noise Mitigation Pilot
Project from Mileposts 158.52 to 158.75, and from Mileposts 163.40 to 163.57, located in
Cuyahoga County, Ohio; and
WHEREAS, expenditures for Contract No. 62-09-01 / 62-09-02 will exceed $150,000.00,
and, therefore, in accordance with Article V, Section 1.00 of the Commission’s Code of Bylaws,
Commission action is necessary for the award of said Contract; and
WHEREAS , on April 13, 2009, four (4) bids were received in response to said
Construction Invitation, which bids were reviewed and analyzed by the Commission’s Chief
Engineer, who has submitted his report to the Commission concerning said analysis; and
WHEREAS, the Chief Engineer reports that the lowest responsive and responsible bid for
the performance of the work under Contract No. 62-09-01 / 62-09-02 was submitted by M.P.
Dory Company of Columbus , Ohio in the total amount of $479,326.60 , which bid is below the
Commission’s estimated expenditures for construction of the noise mitigation pilot project, and
which bid he recommends be accepted by the Commission; and
WHEREAS, the Commission has also been advised by the Director of Contracts
Administration that bids for Contract No. 62-09-01 / 62-09-02 were solicited on the basis of the
same terms and conditions and the same specifications, that the bid of M.P. Dory Company for
Contract No. 62-09-01 / 62-09-02 conforms to the requirements of Ohio Revised Code Sections
5537.07, Section 9.312 and Section 153.54, and that a performance bond with good and
sufficient surety has been submitted by M.P. Dory Company; and
WHEREAS, the Commission’s Executive Director has reviewed the reports of the
Maintenance Engineer and the Director of Contracts Administration and, predicated upon such
analysis, has made his recommendation to the Commission to award Contract No. 62-09-01 / 62-
09-02 to the lowest responsive and responsible bidder, M.P. Dory Company; and
WHEREAS, the Commission has duly considered such recommendations.
NOW, THEREFORE, BE IT
RESOLVED that the bid of M.P. Dory Company of Columbus, Ohio, in the total
amount of $479,326.60 for Contract No. 62-09-01 / 62-09-02 is, and is by the Commission,
determined to be the lowest responsive and responsible bid received for said Contract, and is
accepted, and that the Chairperson and Executive Director, or either of them, hereby is
authorized: 1) to execute Contract No. 62-09-01 / 62-09-02 with M.P. Dory Company in the
form heretofore prescribed by the Commission pursuant to the aforesaid bid; 2) to direct the
return to the bidders of their bid security, when appropriate; and 3) to take any and all action
necessary or proper to carry out the terms of Contract No. 62-09-01 / 62-09-02; and
FURTHER RESOLVED that the Commission hereby authorizes the Executive Director
and the Chief Engineer to assign TranSystems, Inc. of Cleveland, Ohio , to Contract No. 62-09-
01 / 62-09-02 for the purpose of performing construction administration and inspection services,
with such assignment in accordance with the Engineering Design Services Agreement specific to
this Project between the Ohio Turnpike Commission and TranSystems, Inc.; and
FURTHER RESOLVED that the Commission hereby authorizes the Executive Director
and the Chief Engineer to assign Solar Testing Laboratories, Inc., of Brooklyn Heights, Ohio
to Contract No. 62-09-01 / 62-09-02 for the purpose of performing materials testing and
inspection services, with such assignment in accordance with the 2009-2010 General
Engineering Design Services Agreement between the Ohio Turnpike Commission and Solar
Testing Laboratories, Inc.
(Resolution No. 13-2009 adopted April 27, 2009)