OHIO TURNPIKE COMMISSION
Resolution Ratifying Additional Expenditures under Contract No. 59-10-02
WHEREAS, via Resolution 2-2010, the Commission awarded Contract 59-10-02 to Erie
Blacktop, Inc. of Sandusky, Ohio in the amount of $3,106,715.00 to perform repairs and resurfacing
of the eastbound and westbound roadways, from Milepost 91.2 to Milepost 101.5 in Sandusky County,
Ohio; and
WHEREAS, the Contract Documents for the Project required removal of two inches of existing
asphalt, however, following commencement of the work it was discovered that the underlying asphalt
surface material did not present a suitable base upon which to bind the new pavement materials, and
that an increase of the removal depth was required in order to expose a suitable base pavement on
which to resurface; and
WHEREAS, at the time the unsuitable base was discovered, a large portion of mainline
pavement was already closed and could not safely be re-opened to traffic, and, without immediate
commencement of the work, the traffic zone would be in place beyond the July 4 th holiday, thereby
creating a severe impact on the travelling public that could result in unsafe conditions due to traffic
backups and an undo delay in completion of the Project; and
WHEREAS, a thorough review by the Commission’s Engineering staff of the revised costs
submitted by the Contractor verified that the unit costs for the revised quantities compared favorably
with previously bid unit prices; and
WHEREAS, for these reasons, pursuant to his authority under Sec. 1.00 of the Commission’s
Bylaws, the Executive Director approved change orders to avoid “circumstances that would create a
life, safety, or health threatening situation or would unduly delay the completion of the Project;” and
WHEREAS, the Executive Director hereby recommends to the Commission that, with the
adoption of this Resolution, the additional expenditures with Erie Blacktop, Inc. in the estimated net
increase of $1,054,541.06 for the required change orders under Contract No. 59-10-02 be ratified by
the Commission; and
WHEREAS, the Commission has duly considered such recommendations.
NOW, THEREFORE, BE IT
RESOLVED that the Commission hereby ratifies the additional expenditures previously
approved by the Executive Director pursuant to Contract No. 59-10-02 with Erie Blacktop, Inc. in the
estimated amount of $1,054,541.06 in order to effectuate the required change orders to the Project.
(Resolution No. 22-2010 adopted June 21, 2010)