WHEREAS, in August 2004, the Commission issued a Request for Proposals (“RFP”) to
select a professional engineering firm to perform Site Engineering, Design and Environmental
Services for Reconstruction of the Mahoning Valley and Glacier Hills Service Plazas located at
Mile Post 237.2 in Mahoning County, Project No. 71-04-09; and
WHEREAS, the Commission selected
ms consultants, inc.
of Youngstown, Ohio to
perform said Site Engineering, Design and Environmental Services and an Agreement between
the Commission and ms consultants, inc. was executed on January 26, 2005, in the amount of
$93,648.61
for the preliminary development phase of the Project; and
WHEREAS, since performance of the preliminary Site Engineering, Design and
Environmental Services, the Project did not progress due to a lack of capital funding, however,
the Commission is prepared to finalize the site plans for reconstruction of the Mahoning Valley
and Glacier Hills Service Plazas; and
WHEREAS, the Project for Site Engineering, Design and Environmental Services at the
Mahoning Valley and Glacier Hills River Service Plazas is being re-designated as Project No.
71-10-01; and
WHEREAS, ms consultants, inc. has submitted a proposal for further environmental,
surveying and final site engineering design services for the Mahoning Valley and Glacier Hills
reconstruction project in the total estimated amount of
$233,113.00
; and
WHEREAS, the Chief Engineer has reviewed the proposal submitted by ms consultants,
inc. and has recommended that the Agreement with ms consultants, inc. be amended to authorize
that firm to perform the aforementioned services; and
WHEREAS, the Executive Director concurs with the Chief Engineer’s recommendation
that the Site Engineering, Design and Environmental Services Agreement with ms consultants,
inc. be amended to allow for the finalization of the site plans for the Mahoning Valley and
Glacier Hills Service Plaza reconstruction project; and
WHEREAS, the Commission has duly considered such recommendations.
NOW, THEREFORE, BE IT
RESOLVED that the Commission hereby authorizes and directs the Executive Director
and the Director of Contracts Administration to amend the Site Engineering, Design and
Environmental Services Agreement with ms consultants, inc., herein re-designated as Project No.
71-10-01, to include the performance of the additional services required to finalize the site plans
for reconstruction of the Mahoning Valley and Glacier Hills Service Plazas.
(Resolution No. 4-2010 adopted February 22, 2010)